How often Passive House & EnerPHit comes up on the Construction Studies papers, every year it was asked, and questions to try.
HL Asked on 8 of the last 9 Higher Level papers, most recently in 2025. most years
June 2028 is the first exam on the new Construction Studies course. These come from the 2016–2025 papers, so read them as a guide.
Quick ones on Passive House & EnerPHit.
- 50 kWh/m² per year
- 15 kWh/m² per year
- 125 kWh/m² per year
- 10 air changes per hour at 50 Pa
- 3 air changes per hour at 50 Pa
- 0.6 air changes per hour at 50 Pa
- The Passive House standard for retrofits
- An Irish grant scheme for heat pumps
- The nZEB standard for new-build Irish homes
Show the answers
(a) 15 kWh/m² per year
(b) 0.6 air changes per hour at 50 Pa
(c) The Passive House standard for retrofits
Higher Level
Asked on 8 of the last 9 Higher Level papers, most recently in 2025. most years
Every paper, year by year
| Year | Where it came up |
|---|---|
| 2025 | Q10a |
| 2024 | Q10a |
| 2023 | Q10a |
| 2022 | Q10a |
| 2021 | Not asked |
| 2019 | Q10a |
| 2018 | Q10a |
| 2017 | Q10a |
| 2016 | Q10a |
Links open the State Examinations Commission’s paper for that year.
More Passive House & EnerPHit questions
Passive House & EnerPHit, 3 marks
Is every A-rated nZEB house a Passive House?
- Yes, because the two standards are exactly the same
- Yes, as long as it has a heat pump fitted
- No: Passive House has its own stricter criteria
Show the answer
No: Passive House has its own stricter criteria
nZEB is the Building Regulations minimum and the BER is a rating; Passive House is a separate certified standard with fixed limits on heat demand and airtightness.
Passive House & EnerPHit, 2 marks
Software used to design and verify a Passive House?
- The BER certificate
- PHPP
- DEAP
Show the answer
PHPP
The Passive House Planning Package is a detailed model of heat losses and gains. DEAP is the Irish BER tool, and a building can be assessed in both.
Passive House & EnerPHit, 2 marks
Passive House principles: insulation, no thermal bridges, airtightness, MVHR and?
- High-performance windows
- A heat pump for space heating
- Solar PV panels on the roof
Show the answer
High-performance windows
Triple glazing in insulated, well-installed frames completes the five. Heat pumps and PV are common in Passive Houses but are not among the principles.
Other Construction Studies topics
- Health & safety
- House design & room layout
- Insulation & energy upgrades
- Low-energy & eco-friendly design
- Timber, joints, tools & finishes
- U-values & heat-loss costs
- Water supply & plumbing
- Foundations & concrete
- Vernacular & heritage buildings
- Windows & glazing
- Renewable energy systems
- Airtightness & ventilation
- Drainage & wastewater treatment
- External walls
- Pitched roofs
- Plaster, paint & floor finishes
- Stairs & landings
- Doors & thresholds
- Orientation, solar gain & shading
- Stud partitions & internal walls
- Universal design & lifetime use
- Central heating systems
- Ground floors & radon
- Site selection & layout
- Thermal bridges & condensation
- Timber upper floors
- Chimneys & flues
- Daylight & artificial lighting
- Electrical installation
- Flat roofs
- Planning permission & regulations
- House purchase & the industry
- Sound insulation & acoustics