Leaving Cert Technology: Project planning & Gantt charts
How often Project planning & Gantt charts comes up on the Technology papers, every year it was asked, and questions to try.
HL Asked on 7 of the last 9 Higher Level papers, most recently in 2025. most years
OL Asked on 8 of the last 9 Ordinary Level papers, most recently in 2025. most years
Quick ones on Project planning & Gantt charts.
- How much the task costs
- How long the task takes
- How many people are needed
- The tasks that can safely be skipped
- The shortest chain of tasks
- The longest chain of dependent tasks
- 3 days
- 0 days
- 11 days
Show the answers
(a) How long the task takes
(b) The longest chain of dependent tasks
(c) 3 days
Higher Level
Asked on 7 of the last 9 Higher Level papers, most recently in 2025. most years
Every paper, year by year
| Year | Where it came up |
|---|---|
| 2025 | A11 |
| 2024 | A6 |
| 2023 | Not asked |
| 2022 | A7 |
| 2021 | A5 |
| 2019 | A5 |
| 2018 | Not asked |
| 2017 | B3d |
| 2016 | B3d |
Links open the State Examinations Commission’s paper for that year.
Ordinary Level
Asked on 8 of the last 9 Ordinary Level papers, most recently in 2025. most years
Every paper, year by year
| Year | Where it came up |
|---|---|
| 2025 | B3c |
| 2024 | B3d |
| 2023 | B3d |
| 2022 | A8 |
| 2021 | A6 |
| 2019 | Not asked |
| 2018 | A6 |
| 2017 | A8 |
| 2016 | A5 |
Links open the State Examinations Commission’s paper for that year.
More Project planning & Gantt charts questions
Project planning & Gantt charts, 2 marks
What does a Gantt chart show?
- Material costs as a pie chart
- The forces acting on a structure
- Project tasks as bars against time
Show the answer
Project tasks as bars against time
Each task is a horizontal bar whose length shows its duration. You can see what happens when, which tasks overlap and whether the project is on schedule.
Project planning & Gantt charts, 3 marks
Task A takes 3 weeks. Task B takes 2 weeks and can only start when A ends. How long do both take?
- 6 weeks
- 5 weeks
- 3 weeks
Show the answer
5 weeks
B depends on A, so they run one after the other: 3 + 2 = 5 weeks. Tasks that do not depend on each other can overlap and shorten a project.
Project planning & Gantt charts, 3 marks
Why break a project into smaller tasks before starting?
- To plan and track progress more easily
- To make the project take longer
- To avoid setting any deadlines
Show the answer
To plan and track progress more easily
Each small task can be given a time, a person and resources. This makes it easier to schedule, spot delays early and meet the deadline.
Other Technology topics
- Computers, data & security
- Electronic components & circuits
- Gears, pulleys, cams & drives
- Health & safety
- Joining & finishing
- Materials & properties
- Ohm's law, resistors & power
- Sketching & graphic techniques
- Sustainability & environment
- Technology & society
- Communication technologies
- Energy sources & renewables
- Processes, tools & CAM
- Quality, reliability & life cycle
- Structures & forces
- Design process & briefs
- Levers, linkages & moments
- Work, power & energy cost
- Ergonomics & aesthetics